Floor and ceiling finishes are complete across all apartments in Laguna Bay. Aluminium and glass window and balcony fittings are in place in all apartments from the 2nd to 8th floors. Steel core entrance doors, and all internal apartment doors are also fitted from the 2nd to 8th floors, whilst all bathroom and kitchen fixtures are now in place in apartments from the 6th to 8th floors.
Work continues on installing kitchen and bathroom fixtures in all apartments from the 5th floor downwards. Air conditioning units, light switches and plug sockets are now fitted and functional across the majority of apartments. Tiling of the rooftop swimming pool is now 40% complete, with the rooftop gymnasium and changing room walls now in place.