Welcome to the sixth issue of the Heights Holdings newsletter.
  
Please read on for the latest construction updates across the Heights Holdings development portfolio:

 
Laguna Bay - Construction Update
 
Floor and ceiling finishes are complete across all apartments in Laguna Bay. Aluminium and glass window  and balcony fittings are in place in all apartments from the 2nd to 8th floors.  Steel core entrance doors, and all internal apartment doors are also fitted from the 2nd to 8th floors, whilst all bathroom and kitchen fixtures are now in place in apartments from the 6th to 8th floors.

Work continues on installing kitchen and bathroom fixtures in all apartments from the 5th floor downwards. Air conditioning units, light switches and plug sockets are now fitted and functional across the majority of apartments.  Tiling of the rooftop swimming pool is now 40% complete, with the rooftop gymnasium and changing room walls now in place.  

 

 
Click here to view latest updates for Laguna Bay in our construction update image library.
 
 
 
Wong Amat Tower - Construction Update
 
The Wong Amat Tower structural skeleton is now built up to the 26th floor. Interior walls are complete up to the 16th floor, with pre-cast walls also in place on floors 17 and 18. Installation of plumbing and electrical systems is underway up to the 18th floor. Work continues on the foundations of the separate covered parking complex.

We expect a selection of in-house 6th floor show-suites to complete in mid-December 2012, with unit types B (47 sqm), H (65 sqm), G (92.5 sqm) & F (92 sqm) on display.

 

 
Click here to view latest updates for the Wong Amat Tower in our construction update image library.
 

 
The Peak Towers - Construction Update
 
Structural work on Basement floors 1, 2 and 3 of Tower A of The Peak Towers is complete, along with all foundations. The lift core structure of Tower A is now complete up to the 2nd residential floor.

In Tower B, foundation works are 80% complete.  Concrete slab  work on the basement of Tower B is 30% complete. The lift core structure of Tower B is now complete up to the 2nd residential floor.

 
 
Click here to view latest updates for the Peak Towers in our construction update image library.
 

 
Laguna Beach Resort Jomtien - Construction Update
 
All piling and foundation works are complete for Building A of Laguna Beach Resort Jomtien. Pouring of concrete for the basement floor is complete and all steel retaining walls are in place for the basement floor. Pouring of concrete for the basement walls of Building A is expected to commence imminently.

Excavation work continues at Building B and work on the foundations has begun. The cutting of piles is in progress, with dynamic load tests complete. 

 
 
Click here to view latest updates for Laguna Beach Resort Jomtien in our construction update image library.
 
 
We hope you have enjoyed this issue of the Heights Holdings monthly newsletter. To enquire about any development in the Heights Holdings portfolio, or to request availability & pricing, please contact info@heights-holdings.com or call +66 85 282 6454.
 
Until next time, Sawasdee Krap from the Heights Holdings team here in Pattaya!